  1. Many congratulations to Nikhil sir and team for the strong set. Sir, this is just a small understanding on larger generators. You're saying it takes 18 to 20 months to make a large generator. So just want to understand, add to this the time to get the plant up and ready, when should the revenue be impacted because of the larger generators? When should we start thinking about additions from that?

    Read in transcript
  2. No problem, sir. And sir, just second thing, on the capex side for the already existing capacity, if I remember right, you are planning to do INR50 crores capex both in FY27 as well as FY28. So just to understand, is there a debottlenecking scope beyond INR3,200 crores as well that you can do in FY28 sometime?