Sir, just want to get your sense on the re -imposition of section 11. It has been extended for the thermal, but not for the gas -based station. So want to know your view on this and if you can elaborate more on the recent PSP tie up which we did with Mahara shtra that would be helpful?
So would it be fair to assume that considering that the section 11 can be imposed only mainly during the peak time period, say 4 months of the summer, and then probably it may get extended for September, October, probably, I am saying, subsequent year as well, so DGEN utmost can operate at around 35%-45% kind of a PLF, in the best-case scenario, I am saying or even that is on a slightly higher side?