Hello, sir. So, regarding your provision, you have done in the Gurgaon Sector 37D. And till date, we have done about 224 crores of provisions. And also, we have filed claim of amounting INR 700 crores. So, against whom we have filed this claim and what is the expectation within this claim? NBCC (India) Limited 18 10.11.2023 The claim against that contractor that is Rama civil Infrastructure INR 750 crores. It is under subjudice. And this is only provision for making the payment and settle the homebuyers.
Okay. So, till this settlement happens, we will be making quarterly provisions or is it the last one? K. P. Mahadevaswamy, Chairman and Managing Director I think this is the last one.