Good Evening Sir. I have just two basic questions. Firstly, I wanted to understand that if in an EPC project suppose the project size is 2,000 crores in the transmission segment, then how much cost is incurred on the towers, cable, and wires on the substation in that 2,000? If you can give the rough idea.
The second question will be on the STATCOM, while se tting up these substations, what percentage of cost would be or what percentage of a mount would be spent on this STATCOM as a percentage of total cost on setting up this substation?