Stockrabit · Analysts
Questions across 4 calls

Harshal Mehta

Smart Sync Services

KEC International Limited

KEC International Limited CC-Sep24.pdf · 2024-11-05
Congratulations sir for a great set of numbers and solid order book, first of all. Sir, can you give some -- yes, sir, so can you give some updates on our existing 2 Kavach projects? As in how much of them are finished or any rough percent -- in rough percentage terms? And also by when it can be finished?
And also, if you can explain -- you clearly mentioned that the new set of tenders that are coming in for Kavach, they are having 2 different set of biddings, as an OEM side will be different and the EPC side will be different. But our existing billing proc ess, if you can explain that, specifically to this Kavach project, the payment that we are getting or that we will be getting will be directly from railways or we'll be getting from our JV partners and they will be getting from railways?
KEC International Limited CC-Mar25.pdf · 2024-07-29
Good morning, sir. Thank you for the opportunity. Sir, so I have one question. Pardon me for my ignorance, but in the last con -call, you have mentioned that in that particular month, you were doing around 100 kilometers of Kavach implementation work. And I guess that would be the month of May, if I'm not wrong. So, I just wanted to know that whether the project that we were already having on the Kavach side, was that executed and was any kind of revenue booked in that particular segment?
Okay. And any kind of split -- so, as far as I know that one kilometer of this Kavach implementation work is costing around INR50 lakh to the government. So, any kind of break - up that you might be able to give that what part is of our JV partner and what is the part of our own as in for execution work in percentage or maybe in ratio?
KEC International Limited CC-Jun24.pdf · 2024-07-29
Good morning, sir. Thank you for the opportunity. Sir, so I have one question. Pardon me for my ignorance, but in the last con -call, you have mentioned that in that particular month, you were doing around 100 kilometers of Kavach implementation work. And I guess that would be the month of May, if I'm not wrong. So, I just wanted to know that whether the project that we were already having on the Kavach side, was that executed and was any kind of revenue booked in that particular segment?
Okay. And any kind of split -- so, as far as I know that one kilometer of this Kavach implementation work is costing around INR50 lakh to the government. So, any kind of break - up that you might be able to give that what part is of our JV partner and what is the part of our own as in for execution work in percentage or maybe in ratio?