Sai Life Sciences Limited CC-Jun25.pdf · 2025-08-08
Yes. Thanks for taking my question. Sir, on the CDMO manufacturing capacity expansion, last quarter, let's say we were at 600 kiloliters, which this quarter we have added around 90 kiloliter. And on top of that, we have announced another 200 kiloliter by third quarter of 2027. So, that would imply, let's say, a 50% kind of an increase versus FY'25 capacity. So, is that understanding correct? And why I am asking this is because at one point in time, you also indicated that the CDMO capacities actually are going to increase by 80% by FY'27.
Okay, sure. And let's say of this 550 incremental, you have talked about plans for, let's say, 100 KL got commissioned. You are working on another 200 KL. So, the rest, when do you plan to start the commissioning?