  1. Yes, thank you. Congratulations, sir, for a very good set of numbers. So, first question is , this plant commissioning has been getting delayed I think almost since November of 2025. So are there any specific reasons , and we have seen these delays in timelines , multiple times. So, is there a further risk that we are seeing from this August or September commercial production timeline to it getting pushed forward?

    Read in transcript
  2. Right, right. And sir, how I think you did answer to the previous participant in terms of the ramp- up. So, I think because your voice is feeble, I missed that. What did, was it 30% ramp-up in the first month or 50?

    Read in transcript
  3. Okay, so 30% ramp-up by the end of this financial year, right, for the new plant?