Hi CVK, thanks for the opportunity. Just a couple of questions on the datacenter. General understanding in market is that 1 gigawatt of capacity will cost roughly $60 to $80 billion if we were to provide AI datacenters on a full stack mode. So, 50-megawatt capacity should require nearly INR30,000 crores of overall investment even if that is spread over multiple years. Is that a fair assessment or since we are targeting this to more of training SLMs, will the economics be any different?
Okay, so the second question is there's almost 100 gigawatt s of announced AI datacenter investments in the pipeline and recently some of the companies like SpaceX and Meta, they decided to sell or lease their compute. So, in the backdrop, the growing perception is that compute may not be as scarce as it is made out to be, or maybe we are at the frag end of compute-related bottlenecks. By the time our proposed 50-megawatt capacity becomes fully operational, if the compute demand cycle were to turn for whatsoever reasons, how do you think of the tenancy ratios here and ROICs of the proposed investment?