TITAGARH RAIL SYSTEMS LIMITED

TITAGARH RAIL SYSTEMS LIMITED CC-Dec24.pdf · 2025-02-13
Ma'am, can you share with me the project status of the Aditya Birla project that we have taken multiple projects? I think we are doing those projects in phases 1, 23 megawatts, which was expected to complete in November. So, is that project energized? Another project where we were working on the phase 1 of 21 megawatt out of 86 megawatts, which is again expected to be commissioned by March ‘25. And the one more project of that 182 megawatt, which is expected to be commissioned by June ‘25. Are we on track for all three projects?
Ma'am, I think because of that Q3 is a little bit slow because this 23-megawatt project we are expected to be commissioned in November itself. And so how are we looking at Q4? Is that would be better than Q3 or how we are looking in the execution side in Q4?