Thank you very much. We will now begin the question and answer session. The first question is from the line of Gautam Shroff from Nuvama. Please go ahead.

Congratulations, Amitji, on a stellar qu arter. You've entered a 100 crore club. That is an achievement, I would say. To many more. Amitji, my first question to you and team Anant Raj is, we also read about you announcing a fund raise program. How aggressive are the growth plans and how are you thinking two or three years down the line?

Amit Sarin

As of now, this fundraising is completely focused. It's going to be INR2100 crores out of which promoters are going to put in 100 and we will go to the market for the balance 2000. The main focus of this fundraising is going to be for the data center business. As you know, one new development this year has been that the company has come into clouds. The company is fully funded and fully on track for its first 28 megawatts. For that, we do not need any money. But in the coming year, and we are almost there at 28 now, so in the coming year, we plan to add another 35, taking the toll to 63 megawatts. In this 63 megawatts, after launching Ashok Clouds, we are very confident because we've got very good response for Ashok Cloud, the cloud services which the company has launched. When we explained on the call, today we are a single-stop solution for any cloud need of any client anywhere in the world. Of course, the focus is always going to be India. In this situation, we feel that out of this 63 megawatts, 14 megawatts can be, as of now, depending on our fund position and the fundraising which we are going to do, can be easily put into clouds. This takes the data center business and Anant Raj Clouds into a different horizon. In this, you are going to be then competing with all the hyperscalers and the largest ones in the world. That is the category we want to go into. As it is already public knowledge, the technical tie-up for the product which we have launched so far, for which we got very good response, is with Orange, the French company. It's doing pretty well. That is the focus of the fundraising.

Moderator

Thank you, sir. The next question is from the line of Akshat from Niveshaay. Please go ahead.

Akshat

Congratulations, first of all. My question is, is there any realignment in the guidance for the number of data centers capacity to build over the years, like by 2029 or 2030, when it will be like 300 MW?

Amit Sarin

Akshat, we are fully on track, sir. As you know, there are three locations the company is working on. As of now, location number one, which is Manesar, has already started. Location number two, which is Panchkula, is about to start and should be up and running by December this year. So another two months to go, we will be starting Panchkula as well. And the third one is going to be Rai. In the coming year, Rai is going to start as well. So as of now, the focus vis-a-vis the location is going to be these three locations. But what is going to be different is that rather than just being a co -location player, which means that if you are only a co -location player, you are always dependent on hyperscalers for business. But now, with the cloud coming in and kicking and getting very good response, we are going to add on these services. Out of 63, 14 will go, which is almost about 25%. So we plan to maintain the same ratio. But we see a lot of business coming in, sir. Subject to our fund position, we will try and develop more of cloud, because that is much better in terms of cash flow and profitability, compared to the co-location.

Akshat

Thank you, sir. I would ask that what is your...

Moderator

Sorry to interrupt you, sir. Sir, can you use your handset?

Amit Sarin

Actually, can you be a little louder? Sorry?

Akshat

So, what is the capex cost for building a cloud service? What is for one megawatt of that?

Amit Sarin

See, Akshatji, the ballpark figures for a cloud, although this business is actually calculated in terabyte, megabyte, and petabyte, but if you just put it in simple words, one megawatt has an additional investment of close to INR 100 crores. So, that is how expensive it is. But then the horizon is very wide, sir. And we have done 0.5, for which we got very good response. And this is one of the best qualities available in the world which we have been able to launch.

Akshat

Can we compare the type of service with companies like E2E and etc.?

Amit Sarin

Just a bit louder, sir, please.

Akshat

Sir, can we compare the type of service we are providing with companies like E2E networks?

Amit Sarin

This I request Mr. Ashim Sarin to answer. Ashimji?

Ashim Sarin

Yes, sir. The services that we are offering now is basically infrastructure as a service. So, that is the first layer of the cloud services, and that we've already started. And with time, the intent is to move on to platform as a service and software as a service, but that will take some time. But yes, we are at par with what the other players are offering in the market, as far as infrastructure as a service is concerned.

Akshat

Okay. Thank you.

Moderator

Thank you, sir. The next question is from the line of Pavas Pethia from Aditya Birla MF. Please go ahead.

Aditya Birla MF

Hi, sir. The first thing about this fund is 2,100 odd crores. How do you plan to deploy it among various verticals, say data center, residential? What is the game plan there?

Amit Sarin

This is purely data center, sir. This fund is going to be purely for data centers. For our real estate, we are completely funded with our internal sources. We do not need any money, sir. So, this fund will be mainly to get into the cloud business, sir, because this cloud business, fairly for the company, is new. But, you know, thanks to the co-location which the company created, which in terms of quality is one of the best which we were able to deliver. So, that is what generated this demand for coming into data c enters also. And that's how we came into it. And now, today, we have successfully started 0.5, which is up and running now, sir. This is in two categories. Ashim, can you explain the two categories, please?

Ashim Sarin

Basically, sir, what we've done is we've started with a private cloud and almost 50% of whatever we've set up right now, and the remaining 50% is for a government community cloud, which actually qualifies as a sovereign cloud. Because after we started with our co -location business, we saw a lot of requirements from our clients coming in for cloud services where they wanted us to shift them from a capex model to an opex model. That is how we started building up our own cloud services. And now, what we've launched is actually the first step be cause we were very cautious in our approach, and we've started with infrastructure as a service, where we are putting in the servers, we are putting in the routers, the firewalls, the switches. And basically, we are giving the customers come on board, they set up their own virtual machines, and they are able to manage their operations on their own. And the complete infrastructure is maintained and operated by us.

Amit Sarin

Most of the funds which we are going to be raising is co-location. We are up to 28, we are completely funded, we do not need any money. That real estate is taken care of. But now when we want to get into the cloud, we feel that 14 megawatt is going to convert into terabyte and megabyte. That's one thing. But can comfortably, as of now, can be consumed by the market. We do not see any demand problems there. So we want to invest this much to get into cloud, and this will make us one of the largest players in the country doing this.

Aditya Birla MF

So just I missed that number. How is the conversion from, say, a megawatt cloud to crores of capex?

Amit Sarin

Sir, crore of capex is about 100, sir. One megawatt and additional cost of 100 is required to convert one megawatt into clouds.

Aditya Birla MF

Sure, and of this 0.5 megawatt?

Amit Sarin

We did it ourselves from our internal sources, and we got very good response for it, sir.

Aditya Birla MF

So already the rentals are coming on this one?

Amit Sarin

The good part about cloud is that your rentals start from day one. Co-location, you know, things take time because the facilities are made, then you hand it over, then the servers start to come in. But this year, in this case, your revenues start from day one itself. So in this case, the revenues have actually started from 7th of October, sir. So as and when we multiply, we see good demand. We'll keep filling it up, sir.

Aditya Birla MF

And on 100% utilization, this 0.5 megawatt translate to what revenue number?

Amit Sarin

So this 0.5 will actually generate close to INR75 crores of revenue.

Management

Just to add one thing here sir. This cost that we are talking about cloud can go to any extent and this is only for the basic level services. As I said, infrastructure as a service. So the cost and revenues are for infrastructure as a service that we are talking about, but then we would want to move on to the next level also like platform as a service and then later on software as a service. So these numbers that we are talking about is only for the basic level of cloud which we've started operating now.

Amit Sarin

So the basic idea is these are basic numbers, sir. So they will only go higher once we keep on adding services, sir.

Aditya Birla MF

And so on this 28 megawatt, which is supposed to come on by FY25 end how much is already tied up with clients?

Amit Sarin

Completely tied up, sir, fully tied up, sir. We will divert around 25% of t his towards our cloud business, but then we will catch up very fast because the work will continue and by next year we will be almost 63 megawatts.

Amit Sarin

Already, sir. We've already started getting private clients. Sorry, there are NDAs in place. We can't take names and it's not even h ealthy to take names like this, b ut now today we have a mixture of all categories of clients.

Aditya Birla MF

And sir just lastly on this 20 acres of land parcel you were talking about on the presentation there is some 11.5 acres. So is this the same thing which...

Amit Sarin

Sir, 11 is a part of that, yes and other than that we have another 9 which has already been done.

Aditya Birla MF

So at what cost this has come up?

Manoj Goyal

So, see technically there are two kinds of acquisitions we did. One is a large portion one is a small portion which is stuck in between ou r township where the land cannot be independently used. So the land which cannot be independently used and is a small chunk of land that comes very cheap and the chunk of the land comes at a slightly higher price. So we spend about INR20 crores an acre if we translate it in the money terms, average for this.

Amit Sarin

Which is reasonable, very reasonable compared to today's prices, sir.

Aditya Birla MF

Yes, and so it says that CTG properties, 100% equity shares which has a partnership interest. So this is not entire 11.35 which accrues to us. There's a partner, external partner also?

Amit Sarin

There is because buying out the whole thing was not -- would have been too expensive. So there is a partner in this, but then all the development rights and everything will be done by the company, sir.

Aditya Birla MF

Okay, so this 20 crores per acre is including the partnership share or how to see this number?

Amit Sarin

So this is the money we have spent, sir. This is the money Anant Raj has spent for the land average cost to us.

Aditya Birla MF

Development potential for this one?

Pankaj Gupta

So for the entire 20 acre, we'll be using majorly for the group housing and some components will go on the plotter which is part of the township. But looking at the curre nt FSI norm, we'll have about 3 million square foot of the saleable area from the entire 20 acre.

Amit Sarin

This is subject to getting, this means that we've got the land, we are in the pipeline to get the permissions. And the future launches that we hav e this year, we haven't counted them in this. This is for the next year.

Aditya Birla MF

Okay, 3 million is the overall attributable share will be what number?

Management

This will be at the project level.

Pankaj Gupta

So at the project level, it will be 3 plus and we'll be having more than 2 million square feet. Otherwise we'll be marketing the entire thing. So only the share of that will go to the other partner. So typically 3 million will come to our balance sheet and it will go as 2 or 3 each year.

Aditya Birla MF

Thanks. That’s all from my side.

Moderator

Thank you. The next question is from the line of Raj Sarraf from Finvestors. Please go ahead.

Finvestors

Congratulations for the excellent set of numbers. So the 6 megawatts started contributing to the EBITDA as mentioned in the opening remarks. Can you please quantify that for the last quarter?

Amit Sarin

Sorry, Raj ji can you repeat your voice is getting blurred, sir.

Finvestors

So the 6 megawatt data center capacity has started contributing to the EBITDA as you said in the opening remarks. So can you please quantify that for the last quarter?

Amit Sarin

So that was about INR8 crores. It has contributed.

Finvestors

It is in last quarter, sir contributed already INR8 crores?

Amit Sarin

Yes, sir.

Finvestors

And, sir, you just covered in the first question that 14 megawatt out of 63 megawatt will be of cloud by FY26. So maybe know the difference in EBITDA potential between them, the colo and the cloud-based?

Amit Sarin

So the basic difference when you come into the cloud business , one is talking like Mr. Ashim just explained to I'm sure you've been listening to the whole call. Like Mr. Ashim just explained that we are as of now we are just giving it as infrastructure as a service. So here the total top line one is able to achieve in terms of megawatts per year is close to about INR150 crores.

Finvestors

Okay, so like cloud-enabled.

Amit Sarin

Exactly. So whatever additional services once we provide them, we'll talk about them. Hopefully in the next call, we will be talking about that as well, b ut as of now when we only talk about infrastructure as a service, we are talking about a billing amount of INR150 crores per year.

Finvestors

Okay. And, sir, one request sir. Going forward, we will have data center revenue as a major contributor. So can we have revenue bifurcation in our investor presentation separately from real estate and data center or in the quarterly results as a significant revenue. We will have more clarity to what are shareholders?

Amit Sarin

See, real estate will continue the way it is going on. All the information is already on the website of the upcoming projects. So real estate, if we talk about this year sir, we are going to be launching 1.8 million square feet. We are fully on track for that. So that is all on the decided dates. It will all happen. So real estate is going to contribute a good amount of money for the next one or two years. And slowly, slowly data center will catch up and eventually, both the divisions are going to do very well. So Anant Raj Limited will now have two full-fledged divisions. Real estate division which is the historical, the division of the company, the bread and butter of the company as of now and plus the technology division, in which we will be data center, co -location infrastructure and cloud. We'll have both. So slowly 63 next year, 25% of 63 will be towards cloud and the balance will be co-location. See, co-location is something which we understand very well now, sir. And the project which we have delivered is one of the best products which anywhere in the world, one can do. And that is what has got appreciated and opened up the window of cloud also for us. And while we were dealing with our clients, they said that why don't you give this in frastructure also as a service and that's how we ventured out into this.

Finvestors

My request is that if we can have the revenue contribution separately in the investor presentation, so that we should not disturb you in the conference call, that's why, sir?

Amit Sarin

Sir, we have shared with you the per -megawatt thing and the company cannot give future numbers like this, I think.

Finvestors

No. Sir, this was for the concluding quarter like that we have now investor presentation. My first question was to ask you what was the revenue contribution last quarter. If it had been reflected in the presentation this question was not there with you, t he concluded quarter, what was the revenue contribution for the data center that is only my request?

Amit Sarin

The point has been taken. What you are requesting is to split the real estate and data.

Management

Yes, sir because the data center would be the major contributor going forward, sir.

Amit Sarin

Sir, both the revenues are going to be substantial and we will be breaking them up, sir. We will do that definitely.

Finvestors

Thank you very much, sir. And if you allow me to ask one more question, then it will be helpful.

Amit Sarin

Please sir.

Finvestors

Sir, what is the planned timeline we have for 100-acre land in Delhi NCR for future residential and warehousing with revenue opportunity?

Amit Sarin

Sir, Delhi total land which we have is 101 acres, which, you know, as per the present master plan, is eligible for all categories. It is eligible for residential. It is for hotels, service apartments, commercial, retail, and warehousing. But Delhi is one plan which we, as of now, hold, and we want to actually wait. As you know, Delhi is expecting a new master plan, and it is public knowledge. The draft master plan is already available on Janta Book Depot. It's a book anybody can buy. It is yet to be notified. So let us see when it is notified. And as of now, sir, we have enough work vis -a-vis 63-A Gurgaon, and the data center, and now the cloud. So, the focus for the next four years is very clear in the company. We will focus on 63-A because we feel that there is a huge top line with the real estate that the company can unlock there. And data center, of course, this is a sunrise industry in the country. And Anant Raj being one of the first movers in this, we started work in data center in the year 2019, sir. We got our certifications from international bodies. We today have all those things in place. And the product which we have delivered is easily comparable to one of the best products anywhere in the world. So, for the next four years, this is our focus, sir. Delhi, we fully own 101 acres, completely, no dispute whatsoever, 100% in possession of the company. The draft master plan, we want to wait for it to get notified. And that is when we start Delhi.

Raj Shah

Yeah, thank you. Very helpful, sir. And I wish you all the best and happy Diwali. And once again, congratulations on the great set of numbers. And I wish that Anant Raj should get greater heights in the future. Thank you very much.

Amit Sarin

Thank you, sir. Really appreciate your good wishes.

Moderator

Thank you, sir. The next question is from the line of Ruchita from iWealth. Please go ahead.

Ruchita

Hello, sir. Good evening. And congratulations on a good set of numbers. Sorry if I'm repeating the question again. So, my question is mainly on the cloud business. So we are talking about 14 megawatts, which will be coming, going ahead. So this is expected by which quarter? And what is the EBITDA per megawatt that we are expecting for this?

Amit Sarin

Ruchita, like we just said, once we achieve 63, which is in the year March 26. Okay? In that, 14 will be cloud. And as we ramp up, as of now, we have 0.5, which is working. And by the end of this financial year, we feel we will have at least four in this category, of the cloud category. And here, like we just said, that the investment is about, actually, this is maybe not the right term, but for easier for all of us to understand, is that when we talk about megawatts, we spend about 100 megawatts (corrected: 100 crores per megawatt) to give cloud as an infrastructure service. We spend about INR100 crores per megawatt. And in these INR100 crores, we build about 150. Number one, the expense, because, when you do co-location, electricity, and all are pass - throughs. Here, you have to pay for all that. So we are talking about a running cost of about INR2 crores per month, which is INR24 crores. So your EBITDA is about INR 126 crores. So INR150 crores minus INR24 crores is your EBITDA in this situation.

Ruchita

Okay, understood, very clear. And if we can just quantify this quarter for the co- location business, what is the kind of profit that we did, the EBITDA?

Pankaj Gupta

In this quarter, we have done INR8 crores revenue and the operational expenses is around 18%. So, it is around 82%.

Ruchita

And last quarter, what was the revenue for the same?

Pankaj Gupta

The same INR8 crores

Moderator

Thank you, ma'am. The next question is from the line of Prateek Singh from DAM Capital. Please go ahead.

DAM Capital

Hi, sir. Thanks for the opportunity and congrats for the set of numbers. Great, great, sir. So just to get this clarity here, you said that around 100 crores per megawatt of capex per megawatt in cloud, these INR 100 crores is on top of the co-location capex, right? Which is around INR 25 crores to INR30 crores for us.

Amit Sarin

Yes, sir. The co-location is INR26 crores and an additional INR100 crores, sir.

DAM Capital

Got it, sir. So mainly, capex would be the servers, right? The ones you install there.

Ashim Sarin

So this cost is mainly for your servers, your other hardware like your switches, firewalls, and also the software cost and the license cost, that comes in.

DAM Capital

That's good, sir. So, on an operational basis, would we be paying any k ind of fee to Orange or how is this partnership like in terms of economics of this deal?

Ashim Sarin

It is based on the revenue. There is a fixed amount and then it is based on the revenue the company generates.

Amit Sarin

But sir, Orange is only entitled to the technical fees because we actually are going to be owning all the equipment, sir. We are buying everything from them and they are going to be running it technically. So they will only get the technical fees which is actually passed forward.

DAM Capital

Okay. Understood, sir. And sir, when we talk about these servers, I understand that their life in terms of depreciation is only three to four years. Is that correct, that how quickly we need to depreciate them when we make a model?

Ashim Sarin

Normal life would be five years. They can go beyond also. But normal life of a server is five years. And then with the technology changes and all, they can always be upgraded as and when required.

DAM Capital

Yes, sir. And sir, you said that as of now with the 0.5 megawatt you did 50% of it was private and 50% was government. So, do you want to maintain the same kind of a share when you go to 1 4 megawatt or do you think government would be more in that and are the economics different for private versus government?

Amit Sarin

Sir, economics more or less are the same and now we feel that we are getting a good demand from both side. We are not able to fulfil the demand which we have. So this choice, whoever is coming, sir, we are providing and, in fact, we are getting more demand. As we go forward, sir, with 14, we do not see an issue at all of choosing as to who to give and who not to give. Right now, whoever is coming, we are giving and there is enough demand, sir. So it is actually first come first serve. Who comes in first, we give him first.

Amit Sarin

Fully on track, we will do it in January.

DAM Capital

In January. Okay. Understood, sir. Thank you, sir.

Amit Sarin

There was an election, so there was a code of conduct. So that is all done now. So Haryana, as you know, went in for elections. It is all done. So now things are back on track. So we will do it in January.

DAM Capital

Okay. Understood. Great, sir. Thanks a lot for taking the time. Thank you.

Moderator

Thank you, sir. The next question is from the line of Hardik Gandhi from HPMG Shares and Securities Pvt. Ltd. Please go ahead.

HPMG Shares and Securities Pvt

Congratulations on a good set of numbers, sir. Sir, I just wanted to know, first thing is that what would be the rental income which is there in the last quarter? Not the data centers, just the property.

Amit Sarin

Other than the data center, INR12.5 crores.

HPMG Shares and Securities Pvt

And going forward, I do understand that although we are looking to expand into data center and we are going to sell properties, but are we going to also have a significant number of properties just for rental so that there is a perpetuity rental income coming in?

Amit Sarin

Absolutely, Hardikji. As you know, two years from now the company actually did some commercial deals also. But as per the basic policy of the company, we are always very happy leasing out commercial stuff. And touch wood now with the finances all back in place and looking good, we are back to our old policy wherein we will develop commercial and only lease it out. So you will see decent increase. Although as of now the first focus of the company is data centers and cloud, but simultaneously we are working on some commercial buildings and these commercial buildings now will be purely focused on leasing out.

HPMG Shares and Securities Pvt

Understood. And what kind of revenue are we looking at just from leasing going forward? I know it's difficult to... Any ballpark number would suffice because those...

Amit Sarin

Coming two years, the commercial revenue will at least, although future numbers we should not be giving like this, but the revenues from here will at least go close to two and a half to three times.

HPMG Shares and Securities Pvt

Understood. And what are the current numbers, if I may ask?

Amit Sarin

We just told you, sir, 12.5.

HPMG Shares and Securities Pvt

Okay, sir. I thought it was just for the quarter. Or is it the annual?

Amit Sarin

This is for the quarter, sir. For the quarter only.

Amit Sarin

Sir, at least the projects that have been put in the pipeline, coming two years from now, we should comfortably triple this.

HPMG Shares and Securities Pvt

Yeah, that's it from my side. All the best to you guys. Thank you.

Amit Sarin

Thank you very much.

Moderator

Thank you, sir. The next question is from the line of Rashid Parekh from Excel Securities. Please go ahead.

Amit Sarin

Namaskar, Rashid ji.

Rashid Parekh

Hi. Just a quick question. How soon are we looking at this raise of INR2,000 cores, the QIP?

Amit Sarin

Sir, we've taken the enabling resolution. And, as you know, the process will be done. The EGM will be held and all those things, subject to once approved by t he Board. And, sir, we are let's see when we go to the market. As of now, we are comfortable on cash, sir. The company is sitting on a decent amount of cash. So no work is going to stop. So we will see as and when, when we -- because this money is purely for data centers. And now we are doing, we are in the process of placing more orders for which the earnest money we can deposit from our own sources. So as and when we do that, we will go in for the raise, sir.

Rashid Parekh

Yeah, that's it. That's it from me.

Amit Sarin

Sure, sir. Thank you.

Moderator

Thank you, sir. The next question is from the line of Srigopal Bajaj from Stockhifi Advisory Services Private Limited. Please go ahead.

Stockhifi Advisory Services Private Limited

So this is regarding a court matter. Which was last October 26, an article came out which said that the Gurugram court has halted 12-acre residential project. Is it true?

Amit Sarin

Sir, that article, we have written to the newspaper. Also, it is getting rectified, sir. Sir, it was a falsely reported news. The total land involved in that article is only 1,000 square yards, sir. And that also, sir, as you have asked, so we would, thanks for asking, sir, we would actually like to clarify this. The total 1,000 square yards, sir. Obviously what happens in this is, there is a distribution, which is done in our land. So this person, actually the distribution is done by -- in front of the government authorities. And this -- actually the distribution was done, our license was granted, no license of the company has been cancelled, sir. You can take that on record, sir. No license whatsoever has been cancelled. Only 1,000 square yards has been said that the company should not create any third-party right, which the company as it is not going to do, sir. That's it, sir. No license whatsoever, the 12-acres has been cancelled. One is that, it’s written return sector 65. We have no land in 65. Number one. And in this order only 1000 square yards. Right now creation of third party right has been denied. That’s it sir. Nothing else.

Stockhifi Advisory Services Private Limited

Sir, you said INR 2,100 crores that you are raising for QIP, out of this, all goes to data center for 35 megawatts, right?

Amit Sarin

Sir, 35 and so on, sir. Although it will b e completed in 35, but the internal accruals will be so much that there will be no need of money, sir.

Stockhifi Advisory Services Private Limited

Yes, sir. In 35, 14 megawatts.

Amit Sarin

Sir, in 35, 14 will come in cloud, sir.

Stockhifi Advisory Services Private Limited

So, INR1,400 crores for that and INR700 crores for the rest 21 megawatts.

Amit Sarin

Exactly, sir.

Stockhifi Advisory Services Private Limited

Right. Thank you, sir. I'll come back in the queue.

Amit Sarin

Sir, touch wood, God willing, sir, once you have done this, You see, whatever projections you have with your 307, you will complete them with 64, sir.

Stockhifi Advisory Services Private Limited

Okay. Yes. I'll come back in the queue, sir. Thank you.

Amit Sarin

Thank you, sir. Thank you.

Moderator

Thank you, sir. The next question is from the line of Jeewan Garg. Please go ahead, sir.

Thank you very much. Sir, this also, sir, like Godrej and some other real estate player , if they want to come into the data centre, then what is our USP while they all come in here?

Amit Sarin

Sir, see sir, it is a free country, sir. Anybody can co me into any business, number one. But, sir, the thing is that buildings are built with special strength for data centres, sir. It is okay sir. And like we mentioned, that Anant Raj has started this in 2019. So if anyone starts today, it will take them that much time to reach where we are, sir.

Okay, so you mean to say if any new entrants comes, it takes around 3-5 years to come into the profits. Am I right?

Amit Sarin

Easily sir. If someone identifies the land, then they will take approvals, build the buildings. And the buildings of the data center are in a very different strength category compared to other buildings sir. And this is something that Anant Raj, which we know, we spent and we did everything. So, which in every building is not possible. So, most of the people who are trying to come in this, who are making brand new. So, whatever time it will take them, in which 3 to 4 years time will take minimum. Maybe more.

Amit Sarin

Fortunately, sir, India, touchwood, last decade, India has seen a lot of freedom in terms of working. You have seen India's ranking, how much it has gone up. So, there is no such entry barrier from the government. But yes, sir, these are technical things. And, you know, these technical things you can only understand when you do them, sir. Today, in Anant Raj, which we started in 2019 and which we have mastered today - one is, the product which we have delivered is, quality wise, easily comparable to anywhere in the world. So, these things matter a lot, sir. And you can see our website separately, we have mentioned all the partners who we have with us. So, these things are something which, you know, cannot happen overnight. So, I am not saying nobody else, that somebody else cannot do it. But if someone else does it, it will take a lot of time, sir. And this is what Anant Raj has today, that today we are amongst the few people who have all these categories with us.

Sir, any listed player, competitor of ours, whom we can compare our things with that?

Amit Sarin

Sir, I think one should, sir, we have given our product, we are completely sold out of what we have delivered. And we are very -- we see a very good demand of what we are going to be delivering in future also. So, we are comfortable, sir, with what we are doing. So, as I said, to take somebody else's name is not proper in the conference call like this. But we are good, sir. As of now, the product which we have delivered, it is completely done. And whatever we have in the pipeline, we have enough demand for it, sir. In fact, more than enough.

Okay, thank you very much and great set of numbers. Thank you, sir. All the best.

Amit Sarin

Thank you.

Moderator

Thank you, sir. The next question is from the line of Prateek Singh from DAM Capital. Please go ahead.

DAM Capital

Hi. Sir. Thanks for the opportunity again. So, just a bit of this clarity. So, when we say that we recognize the revenue of INR 8 crores for data centers this quarter, the same was there last quarter, on a 6 megawatt run rate, this number should be higher, right? This doesn’t mean that we are…

Amit Sarin

The second one has just g ot handed over to the various clients. The second one has just got handed over. So, in this quarter, you will see that increase coming in, sir.

Amit Sarin

Like we were saying, Prateek Ji what happens is when you do cloud, your revenue starts from day one. But when you do co-location, there is a lead time, sir, which is like handing over, taking over type situation. So, in this quarter, it will run completely, sir.

Moderator

Thank you, sir. The next question is from the line of Prakash Shandilya from an Individual Investor. Please go ahead.

Amit Sarin

Good evening, Prakash. Ji. Namaskar.

an Individual Investor

Thanks, sir, for giving me the opportunity, sir. First of all, I want to congratulate to posting on superlative Q2 results, sir. My question regarding cloud service adoption, sir. As I have gone through the presentation, sir, cloud service as an infrastructure, as a service, operational ized, working on scaling to platform as a service and plan to expand the software as a in future, sir. Can you give me the, in which year we are, can do this plan, sir?

Amit Sarin

Ashim ji will tell you, sir, please.

Ashim Sarin

So, infrastructure as a s ervice is already operational. In fact, we have already started work on going to the next phase. So, it is on the drawing board right now. Because when you create cloud, it can actually go to any limit. It is infinite. So, you just have to keep on adding m ore and more services. And the other thing that we want to add here is, sir, that this actually compliments the co-location business also. Because many of the co -location customers would be using some of our cloud services that we will be offering. So, both the businesses, both of these will actually complement each other also. And platform as a service, we have already started work on it, sir. So, once we complete our study and are able to finalize our roadmap, then we will be going ahead with those also.

an Individual Investor

Thank you very much, sir. This was only the question. And best of luck for the future, sir.

Ashim Sarin

Thank you, Prakash.

Moderator

Thank you, sir. That was the last question for today. I now hand the conference over to the management for closing comments.

Amit Sarin

We would like to thank everyone for taking out the time, especially in the festival time. And we assure you that the company in the past three years has done growth quarter-on-quarter. We are very confident that we will continue this for the coming quarters as well. And data center and real estate is something that the company is always doing. The new thing which the company has added to its portfolio is the cloud services. And we are very robust on this. And the product which we have delivered is easily comparable to any product in the world in terms of quality. We assure you that the company will continue the growth process. And we thank all of you for supporting the company always and giving your good wishes. Thank you once again. And a very happy Diwali to everyone. Thank you. Thank you everyone. Happy Diwali.

Moderator

On behalf of Emkay Global Financial Services, that concludes this conference. Thank you for joining us. And you may now disconnect your lines.