Thank you very much. We will now begin the question-and-answer session. The first question is from the line of from Digant Haria with GreenEdge Wealth.
FY2027 Q1
My first question is on our IPP, the power sale and power realization. So, if I just back calculate the numbers, in this quarter, we earned almost INR 8 a unit on our power sale. Now, I heard on the call that almost 370 megawatts of our capacity, we have some long-term PPAs or mid-term PPAs for that, and I’m sure the rates for PPAs would be between INR 5 to INR 6. Is it fair to say that going ahead, as more PPAs are signed by us, the revenue per unit of power will keep declining?
I think there is some misunderstanding. Our current period income also includes the previous year adjustments. So the average realization calculated by you is not correct one.
Okay.
Reverse calculation will not work because we have certain income for the previous period also.
Okay. Okay. Got it. Sir, but then going ahead, like we should generally assume for the full year, like INR 5 to INR 6 a unit on whatever electricity is generated and sold by us?
Yes, yes.
It will be in between this. And over a period, it will go up as the inflation goes up and peak demand goes up, this will increase, particularly for the hydropower side.
Okay. Okay. Sir, and just I think this summer, it said that there was a lot of solar power in the daytime and which is why the daytime rates did not go up at all despite very high demand. So at Sarda Energy, how do you see this whole situation of excess solar capacity coming? And like will it hit us or that is precisely the reason why we are doing these long-term PPAs?
No. As the solar is increasing, at the same time, BESS is also coming up. And there will be certain policy changes at the government level also when they may also give concessional power tariff during day hours to the industry or maybe charging stations an d all those things, policy initiatives will also happen. So over a period of time, things will get balanced. But yes, definitely for the present time, during day hours, because of solar, power is excessive. And during the peak hours, the it has gone up. So we are getting much higher prices during peak hours. And peak hour period has gone up from 5 hours to maybe 8 hours, 10 hours.
Got it. Okay. Okay. And in case of our hydropower, wherever our hydropower projects are, is there enough water like has it rained in the reservoirs which are there around our hydropower plants?
In case of our large hydropower plant of 113 megawatts, we have generated higher than the last year. We are at par even after closure of the unit for almost 13 days. So indirectly, we can say we have generated better than the previous year. But in case of smaller hydropower plants, there was a shortfall of water because there was a delay in the rainfall. Our generation was hardly 1% lesser than the previous year.
My question is that, see, quarter 2 is the largest quarter for our hydropower generation. So, I just wanted to ask if the rains come and is the water adequate in the reservoirs from where this hydropower will be generated?
Yes, Rains are good. And July, we are getting far better rains in the smaller hydropower projects also.
Okay. Got it. And then my last question will be for this year, which is financial year '27, what will lead to, say, a growth in revenue or EBITDA? Because whatever projects we have on the coal mining side or in the power side, a lot of them are probably going to come later. So, can we expect any growth in this current year?
One will definitely be the improvement in the power price realizations. Another is the improvement in the power capacity utilization in our IPP. These are two primary factors. And with the commissioning of our 30 -megawatt power plant, there will be improvement in the generation.
Metal side, the production will go up with the commissioning of the 30 -megawatt new power plant. Our total power generation will go up. That will definitely help in increased production of the steel side.
The next question is from the line of Manav Gogia from Yes Securities.
Sir, my first question is pertaining to the INR 110 crores impact on the net profit that we have witnessed this quarter. Just wanted to get a sense , if you could give me the number of what the actual impact was on the top line and on the EBITDA level?
In the top line, in the revenue, it was INR 162.64 crores was added in the revenue side. There was an increase of about INR 18 crores in the other income in the form of interest. At EBITDA level, you can directly add up 25% to the INR 110 crores. That is the EBITDA level effect.
Okay. Net of tax, right?
Net of tax.
Got it. Sir, just a follow-up. This INR 18 crore is the only number which is coming into the other income because sequentially, we have seen a good jump in the other income from roughly INR 4 crores, INR 5 crores. So...
INR 18 crores is basically interest awarded along with the tariff. So that is added in the other income.
Okay. Got it. So that is quite helpful. Second question, sir, comes pertaining to the PPAs. So out of 380 megawatts of PPAs that you already have in place, what megawatt capacity would it be pertaining to SKS, roughly 200 megawatts, if I'm not wrong?
No, 330 megawatts approximately.
Okay. 330 for SKS. And would you be able to give us a sense on what the tariff would be?
It is in between INR 5 to INR 6.
Okay, between 5 to 6. Okay. And the maximum capacity that we are looking for PPAs for SKS, is it going to be 400, 500, or are we going to keep something as probably open quantity over there as well for sale?
Maximum quantity is 540 megawatt.
Okay.
Now it's a call we have to take, to what extent we have to commit.
Sure. Got it. That is helpful. So one last question I had was on the mining front. The PPT states that we are going to be reaching a coal mining capacity of 7.1 million, which includes the 2.1 million from Bartunga.
My question arises the 5 million ton target that we plan to achieve, what all mines would be there? Is it Gare Palma IV/7 is what we are aiming for? And if you could also give me the timeline at which what procedures will be go from 1.8 million to 5 million?
So, Gare Palma IV/7 is 1.8 million tons. 0.6 million tons will be from Shahpur West. 0.6 million will be from Senduri approximate. This is provisional because it is under exploration. That may change. But assuming on the initial side, 0.6 million and 2 million will be from Gare Palma IV/5.
This has been in our presentation also. In our presentation at Slide number 23, all details are made available.
Yes, yes. No, no. That I'm aware of. I wanted to get a sense because you were planning to expand Gare Palma IV/7 from 1.8 million to 5 million. I just wanted to get a sense of how that expansion is going to take place.
No. As of now, we are not considering in the immediate future. That is because we have got new mines with a better quality of coal, compared to the Gare Palma IV/7. For the time being, we are focusing on the new mines.
Okay. And these new mines will be operational only post FY28, right? Not no prior.
Shahpur will start by end of current financial year, FY27.
Okay. And the coal from Shahpur West will be usable for our SKS power plants or no?
No. That will be for our Sponge iron and ferro alloy plant, because that is high grade coal. For power plant, we don’t require high grade coal.
Okay.
Just to clarify, Manav, all the new mines, they are all high -grade coal mines. And Shahpur is like already told is starting in the current financial year. And Bartunga, we will open in the end of next financial year.
The next question is from the line of Deepika Rathore from HG Security
Could you share the latest update on the environmental clearance for the 600 -megawatt brownfield expansion for SKS? And when do you expect construction to commence?
So, the study that is required to submit our TOR is already over. We are in the final stages of making TOR. And as soon as we submit it, maybe in another 3 months, they will accept it looks like. And then maybe we have to go for a public hearing and post public hearing, so maybe we have another 6 months to 8 months to get a final environment clearances. And post that, we'll be able to, in the 6 to 8 months, appoint a consultant also for the same. And then all the procedures will start.
Good afternoon, sir. Continuing with the question about the new plant, by when can we expect that it will be completed and power generation will begin?
Sir, as told in the last con-call. We are expecting to complete by FY31.
FY31. So, then we expect our turnover to be more than double, sir?
Should be by that time.
The next question is from the line of Ashish from Bonanza
Yes. So, my question was regarding the Sikkim project. That was disrupted due to the transmission line. Has that project normalized post the restoration of the transmission line?
Yes. We are producing at full capacity.
Okay. So, there won't be any residual impact during Q2, expected residual impact on Q2?
No, sir, it doesn't look like.
The next question is from the line of Ashwini from FinAvenue
I just had one question. Steel prices remained range bound during this quarter, while ferro alloy prices had improved modestly. So how do you see the pricing environment evolving in the second half of FY27?
So both steel and ferro alloys prices, , we personally believe that they will be stable. And the margins may look to be a little more decent in terms of ferro alloys. And steel, it looks that it will be stable. And if so that we have a complete settlement in the West Asia region, we might see prices also going up because there will be demand pickup and more stable production centers in West Asia region as well.
Okay. Understood. Also, I had one more question. What were the specific right -of-way challenges for the 50-megawatt solar project? And is there any execution risk beyond the revised commissioning time line?
There is a railway line coming in that region for which they are acquiring a lot of land. So, we assume it has been notified already in that area. They are acquiring land. And I think in next 1 to 2 months, we should get permission from the railways for the same.
Okay. One last thing. I wanted to understand like guidance for PAT and EBITDA for FY27, if you could just help with that as well?
Generally, we don't give any forward guidance. We have given the industry scenario and our project. As already stated, the current period, current quarter prices are also better. As stated in our opening address also, July prices in the power have been better. We are in a volatile market. So giving any guidance on the specific numbers is not advisable.
The next question is from the line of Vishal Patel from Patel Investments
Firstly, sir, congratulations on good set of numbers. So I have a couple of questions. First is, excluding the impact of one -off items during quarter 1, how should we think about the normalized quarterly EBITDA run rate over the balance of the FY27 as operational?
So, second quarter is definitely better because of hydro generation. And as stated, power prices are better, have been better in July, at least, whatever has already gone up as against last year INR 4.20, this year, it was INR 5 in IEX itself. So we expect the power prices to be better. Beyond that, it's very difficult to comment on the profitability side. Otherwise, as I already stated, with the commissioning of the 30-megawatt power, our steel volumes will also go up.
Okay. Sure. Sir, my second question is, with improving power demand and additional PPAs, how do you see PLFs and merchant realization evolving over the next few quarters?
PLF should definitely, if you see PLF at the annual level, PLF for the whole year for IPP shall be better than the previous year. This is what we expect. Last year, I think , we had 415 crore units. This time, we should be able to cross that with a reasonable margin.
Could you quantify as in just surpass or like with a healthy growth?
As I stated, in case of IPP, last year, we had generated about 415 crores of units. This year, generation will be better than the previous year. And in case of captive power plant also with the commissioning of the 30 -megawatt new generator, our capacity utilization will be better as compared to the previous year. In case of hydro, it depends solely on the rainfall. And as of June, our generation was almost at par with the previous year.
Okay, sir. The next question is from the line of Deepika Rathore from HG Securities.
So, with most of your major projects progressing as planned, what do you see as the biggest execution risk to achieving your FY30 growth road map?
As of now, there is no material risk we see, except there may be slight here and there because of the regulatory approvals. Otherwise, more or less the things are moving as what we have planned.
The next question is from the line of Reena Kaur from Starklume Investments
So, I just have two questions. One was now since everything is on track, like the 30-megawatt turbine replacement is commissioned, the Sikkim hydro project resumes normal operations, and the maintenance shutdowns have also concluded. What do we expect earnings in Q2 becoming half yearly for FY27?
As stated, we don't give any forward -looking profitability. because it depends on a variety of factors, rainfall data, power demand supply. There are multiple factors. And in case of steel also prices are volatile because of the developments. So , giving any specific number will be very difficult. But we have already stated on the operational front, we have already clarified. Operationally, it should be better. This is what we can tell.
Okay. Steel prices were relatively stable during the quarter, while ferro -alloy prices showed some improvement. How do you think the pricing scenario will evolve in the rest of FY27?
The prices will remain stable for both ferro alloys and steel. And in fact, the margins may be a little higher in the Ferroalloys segment as we are seeing some softening of raw material prices. And for steel, I think once the West Asia matter is completely settled and they have a peace accord, which is in place, then we might see some uptick in the steel pricing as well. Plus, overall, the steel demand looks to be very good because of domestic developments as well. We have very strong and robust domestic demand and with new developments of data centers and many other infrastructure projects, especially after monsoon, we see that the prices go up.
The next question is from the line of Mann from Sunidhi Investments
So, I wanted to ask you on the Arunachal project. So, most of the approval has been received for 66 megawatts. So when do you expect construction to begin? And what do you think will be the expected time line for it?
So we are undergoing all the drilling and soil investigation. And we have also appointed a consultant. So as soon as those data are available, detailed engineering will commence.
Do you expect from this year or from the beginning of next year?
This year itself.
The next question is from the line of Priyansh, an Investor.
I wanted to know that regarding the transmission tower that was recently lost, what is the loss that has been incurred in electricity generation pertaining to this? And consequently, what is the additional cost that was incurred to build it again? And are there any, let's say, steps in place to prevent this from happening again?
There is no material cost incurred on the restoration of the tower. Nominal cost is incurred and most of that will also be covered except the minimum excess loss that will be covered through insurance. Yes. But whatever generation we have lost for a few days, that was the real loss what we have incurred, which is already covered in the first quarter results broadly because started again. So, there is an impact of 5 days generation in case of July. Otherwise, everything is already covered. And amount is not substantial. restoration cost is negligible, and that is also fully covered in the insurance.
Okay. Got it. And my second question was regarding the mineral wool project. What was the revenue of the mineral wool? And what is the sales and EBITDA target of mineral wool for the Q2 and the full financial year FY27?
So, we have started and we've been ramping up our production in the mineral wool. And in mineral wool, we are now touching almost 60%, 65% of our capacity. And once we achieve the full capacity in the coming year, in the next 3 to 6 months, we'll be achieving that full capacity, we should be able to give out the exact numbers. Right now, we are still identifying a few issues,
and we are trying to resolve those issues. So right now, the project is not making any profits at the moment.
Got it. But is it making sales or not at this moment?
Yes. We are doing sales. There is a huge demand. There's a huge demand and we are making good sales. In fact, we are lagging in sales. The demand is more and our production is not ramping up due to certain imported equipments and machineries, which are stuck due to West Asia crisis and all. But we should be getting that in order. And probably in the next 6 months, we should be achieving full production.
Okay. But do we have any revenue figures right now?
We are expecting for FY'27, we should be achieving around INR 90 crores.
INR 90 crores. Okay. And for Q2... Manish Sarda For Q2, it's very difficult to comment right now.
Okay. So, the projection is the capacity utilization should ramp up from.
Ramp up in the next 2 quarters, and we should be able to achieve in FY27, anywhere between INR 90 crores to INR 110 crores.
Thank you, everyone. That was the last question. Thank you, everyone. Thank you, management speakers. On behalf of Sarda Energy & Minerals Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.