Thank you very much. The first question is from the line of Mohit Kumar from ICICI Securities. Please go ahead.
SJVN Limited analyst Q&A
First question, is the total renewables portfolio, which you had won, I think where you participated and one is around 7 gigawatt, right? While you just mentioned that the under construction portfolio is 2.2 gigawatt. So where is the gap? Is it there's a gap in signing the PPA? Is the PPA signing getting delayed?
Thanks for your question. Yes, we have already received the tenders and the gap is because of the PSA, power sale agreement and signing of PPA. So once we tender for as REIA, then we approach various DISCOMs. And once the power sale agreement is signed with the interested DISCOM, then we sign the PPA, power purchase agreement with the developer. So as the PSA is not realized, so therefore, we have not signed the PPA and has not given go ahead to the developer for installation of the plant. Thank you.
Sir, in your opinion, of course, it's a large gap. Do you think that most of the PPA will get signed in the next coming months? Or do you think there could be further delay?
Yes, we have approached to various DISCOMs. And recently, there is a meeting conducted by Ministry of Power and MNRE also. And now MNRE is also going to conduct a meeting with the various state utilities. And so that MNRE will embrace the state utilities t o sign the PSA. And once the PSAs are signed, then certainly we'll immediately sign the PPA with the developers. So we are expecting that the things will improve within the next -- within 2 months.
My second question is when do you sign -- when do you expect this Buxar to get commissioned? And the related question is when do you expect the Nepal power plant to get commissioned?
Which power plant?
Nepal hydropower plant.
Yes, Arun 3, 900 megawatts, it is under construction. And powerhouse and the water conductor system are moving very nicely, and we are on time at these structures. But unfortunately, at dam site, we are facing certain geological challenges. And because of that geological challenges, the commissioning is expected to be -- to get delayed. And during the last quarter of the financial year '27, we will commission the Arun 3.
And sir, on the Buxar, what is the time line?
Time line as of now, December 2027, we are targeting...
Buxar sir.
Sorry, Buxar is -- Arun 3, I was telling. Buxar just May month, next -- within 2, 3 months, we are going to commission first unit. 660megawatt first unit, we are going to commission during the month of May. COD during the month of May.
And the second one, sir?
Second one, it will take another 4 months.
The last question from my side...
During this year only, the entire capacity of 1,320 megawatts, we are going to...
Understood. Last question from my side, sir, on the PSP portfolio, are we looking to award some tender in this next fiscal? Are you looking award some start construction on the PSPs?
On PSP, the first activity is preparation of pre-feasibility report. So -- and thereafter, DPR. So we are in the process of preparation of PFR for 1,200 megawatts and 1,000 megawatts -- 2,200 megawatts and 1,000 megawatts. So 2 projects. And thereafter, we will start preparation of DPR. DPR is under preparation for 2,400 megawatts, okay? So once DPR is prepared and cleared, it will take another 4 years for the construction of pump storage plants.
The next question is from the line of Paras Chheda from Purpleone Vertex Ventures LLP.
Yes. So I have our Director of Projects, Mr. Sushil Sharma. So I hand over the mic to Mr. Sushil Sharma to answer this question.
Our CMD sir has already told you that Buxar 2 units of 1,320 megawatts will be commissioned during this FY '25 -'26, then again, this solar capacity will be able to add another 200 or 250 megawatts.
Okay. So about 1,500-odd megawatts will be added this year?
Yes.
Yes, yes.
And this 200-odd capacity, when will that be added, sir?
The work is going on. Maybe in the third quarter, we'll be able to add this much capacity.
Third quarter of FY '26.
Apart from Bikaner -- Bikaner also.
Bikaner also 1,000 megawatts. We are extremely hopeful that once the panels are supplied, then we will also commission in the third quarter of this '25-'26.
Sir, even if not third quarter, fourth quarter also, you are talking about 2,500-odd capacity that can be added this year?
Yes.
So nearly the capacity can double in FY '26.
'26, yes, the overall.
Okay. That is good to hear, sir, because I mean, the interest cost is already reflecting now additionally. So in terms of project execution, I think that's a critical one. And secondly, sir, my other question was there were talks about SJVN Green Energy being listed and demerged. So is there a status on that, sir?
Yes. This listing, we are planning and we are just taking this -- we are weighing all the options. Maybe in the third quarter, we will be able to -- this issue -- we'll try to listing in the third or fourth quarter.
Of FY '26?
Yes, '25-'26, yes.
Okay. So about a year down the line. And for valuation, it is still time?
The next question is from the line of Ragini Pande from Elara Capital.
Sir, what is the reason of increase in interest expenses? It has gone up significantly.
So as you see in that we are in a growth phase and for that, we are borrowing capital for our capex. And as you might have heard just now that we are in the process of commissioning roughly 2 to 2.5 gigawatt of capacity in FY '26. So most of the capital is being infused in -- under construction projects. So that's why the -- interest rate is going up temporarily till FY '26. So once the plant will be commissioned, again, the situation will improve.
And sir, the same question for the depreciation expense as well. What was the reason for that?
I'm R.P. Goyal, Director of Finance. Since we have commissioned our Naitwar Mori during the third quarter of last FY, so full year depreciation -- 9 months depreciation has been charged in this financial year. That's why depreciation has increased. And the simil ar reasons are for the finance cost also. Due to commissioning of Naitwar Mori, there is an increase in finance cost. Furthermore, we have done monetization of -- securitization of our return on equity as per the Government of India instructions. That's why finance cost has increased in the current financial year. And this money, we have deployed in our renewable energy projects.
And can you give the breakup for the incentive in come this quarter and the last [ inaudible 0 24:30]
For current quarter is INR68.49 crores. So you are asking about incentive?
Yes, incentive income?
Incentive. For Q3 incentive is INR68.49 crores. And during last year, similar quarter, it was INR51.18 crores.
Okay. And I don't know whether I missed this, but what is the capacity addition target for FY '26 and '27? And it would be great if you could give a breakup between the renewable and the hydro capacity.
So we would be able to add roughly around 1.5 gigawatt of solar in FY '26. And thermal side, we would be adding this 1.3 gigawatt of thermal. These are -- so if you put together, it is around, say, roughly 3 gigawatt of capacity, which company is going to add in FY '26.
Okay. And any guidance for '27?
So '27, definitely, as you know, we have a large portfolio where, again, in '27, we would be adding Arun 3, so '27-'28 that is. So '27, we will be adding another 1.5 gigawatt of project from our renewable portfolio.
Sir, my question is our target for FY '26.
Sorry to interrupt. I would request you to please use your handset.
Am I audible now?
Yes.
Yes, sir.
Perfect. Sir, my question is for FY '26, SJVN initially had a target of achieving around 12 gigawatt and by FY '30, we are aiming for 25 gigawatt. Currently, we have under construction of around 5 gigawatt ballpark number of -- ballpark capacity that is under construction. And I just want to understand, I mean, how practical should we be in terms of estimating what will be the likely capacity by, say, FY '27-'28 and FY '30? Because I think 25 gigawatt looks farfetched and will not be achievable considering the kind of pipeline we have.
So you have to understand one thing here that as on date, we stand at 2.5 gigawatt and another roughly 3 gigawatt we are adding in FY '26. Our total portfolio on the renewable side, where you understand we can add capacity in a short span of time from 18 months to 24 months, and we have a portfolio of roughly 7.2 gigawatts. So if we take our renewable portfolio, hydro side, you have heard about numbers. And a lot of work is in progress. Sir has just shared that we have signed MOUs and survey investigation and DPR preparation of solar as well as the pump storage and the hydro projects are in process. So as of now, we are doubling our capacity in FY '26. An d every year, we are going to -- by FY '26, we are going to add, say, roughly around 3 gigawatt of capacity every year.
Arunachal.
And Arunachal, we have roughly 5 gigawatt of a portfolio where we are in advanced stage, we'll commence construction in the Italian, and this is the largest hydro project of India, and that will come somewhere around by FY '30 or '31. So we are still quite optimistic to achieve our target of this 25 gigawatt by 2030.
Understood. Sir, when you said 3 gigawatt per year, that is inclusive of both hydro and solar or is it...
Yes. It is inclusive of hydro and solar. And maximum capacity like 25 gigawatt mix, wherein we'll be adding roughly 16 gigawatts from the renewable side, solar and wind. And the rest of it around 8 gigawatts will come from the hydro side and balance would be thermal.
Understood, sir. Understood. Sir, can you help me with the regulated equity for the company currently and projected for next year?
The next question is from the line of Vipul Kumar from Sumangal Investments.
So 3 gigawatt will be added next year. So what should be the depreciation run rate annually for those projects we should consider?
Exact numbers, we don't have as of now. What would be the depreciation for the upcoming commission projects. So we'll revert back through mail.
So why don't you put a detailed presentation, you are implementing so many projects. So likely completion and all those shares, your peers are putting detailed presentation in one of the con calls last year also, I had suggested this. This has become -- I mean, very confusing for investors how to.
We understand. And definitely, we are going to do the investor conference. There we'll share the detailed numbers, as you said.
No, no. But before you do investor conference, at least you could put up a presentation where you can share the detailed status of each project which you are implementing as of today and which are the projects likely to be commissioned year-wise, that is not a very big deal, sir. So please don't take it as criticism. This is our suggestion, sir.
Most welcome your suggestion. Most of the information is available on our website. However, as you said in the presentation form, we will share with the investors. Thank you for your valuable suggestion.
And sir, lastly, in opening remarks, CMD sir said that we have signed a memorandum with Bihar government with tariff of INR9 some paisa. Have I heard it correctly?
No, that tariff number. Tariff number was not discussed. It is a pump storage project. So tariff for pump stage project, you understand is roughly in the range of INR8.5 or INR9.
INR9. Yes.
The next question is from the line of Rupesh Sankhe from Elara Securities Private Limited.
Sir, this quarter, we have seen very good incentive income. Even surcharge income has also gone up, coupled with the higher PLF. So the PBT growth was not that high. So is it because of higher financing cost kind of under recovery?
Yes. It is due to -- you are right, it was due to higher finance cost only.
Okay. Sir, how we are placed in terms of foreign currency exposure, sir?
Can you repeat your question?
[inaudible 0:32:42] As of now, we have borrowing in USD and JPY. We have outstanding of roughly INR3,400 crores in the USD and around INR1,500 crores in JPY. That's our exposure as on date.
The next question is from the line of Mahesh Patil from ICICI Securities.
Just Arun project that you mentioned, largest hydro project, 5 gigawatt you mentioned, right?
These are the total capacity of 5 gigawatts in Arunachal, which consists out of 5 projects.
Okay. And these are expected by FY '30-'31, right?
FY '30 -'31, we would start commissioning these projects. And the biggest one is 3,097 megawatts.
Okay. And sir, for these projects, has the contracts been finalized the EPC equipment contracts? What's the status?
We are in the process of finalizing the packages and getting the requisite approvals. So we would be able to award these projects in FY '26, maybe Q3 or Q4.
Okay. So the tenders are floated, yes?
No, not floated yet. Tenders, we will be floating for lower Arun, which is a project we have in Nepal, 669 megawatt for that tender has already been floated and we would be in the process of awarding the contract for 669-megawatt hydro project in Nepal.
And for these projects, this 5 gigawatt in Arunachal, when can we expect the tenders to be floated?
Tenders would be -- we will come out with the tenders in FY '26 itself. So as I said that we would be targeting to award at least Italian first, the largest hydro project in FY '26.
Okay, sir. And sir, another question is on the RE portfolio. Out of this 7.2 gigawatt, how much capacity do we have the PPA currently?
So as far as RE 100% capacity is PPA backed in our RE project. And we have a very good tariff number also roughly 2.8 -- the average tariff for this project. So our RE portfolio.
So entire 7.2 gigawatt has PPA?
Yes. Entire 7.2 gigawatt has a PPA.
Okay. But you are mentioning something challenge since...
I mean to ask about the REIA vertical. How many PPAs have we signed against the tender floated?
So as shared earlier out of 2.4 gigawatts we awarded, we have not able to close the PPA and PSA for that. For the last year awarded project, we have already closed the PPA and PSAs are roughly 3 gigawatt.
The next question is from the line of Aniruddha who is an individual investor.
Regarding the projects for this current financial year, like '24-'25, we were supposed to add like around 2,000 megawatts. But right now, excluding the Omkareshwar, we are not able to add any -- commission any projects. So what was the reason for the delay?
As shared earlier that we faced some headwinds, especially in our hydro project, Arun 3 and Buxar, both the projects were slated to be commissioned in FY '25. And due to the geological surprises in Arun 3 and the COVID and all related issues in Buxar has pushed us back by 1 year or 1.5 years for Arun 3 and by a year in Buxar. So that is the main reason.
No, no, not related to Arun 3 or Buxar. I'm asking about the solar projects like...
Solar project, the capacity was supposed to be added from commissioning of Bikaner. And Bikaner, as the EPC was awarded to Tatas and their factory, they could not commence the production of modules in time. So it's an issue industry -wide issue. It is under CPSU scheme and Indian modules has to be stalled. So that is the reason that we are not able to add that capacity.
No sir, in the earlier conference call, you mentioned that besides Bikaner and Buxar, there were other projects like GUVNL Phase-XIII, XIV, XV11 and now Jammu, I think, if I'm not wrong, in Bihar. So these projects are delayed. Is my understanding correct?
We have some land issues regarding land completion of land acquisition and those. So we are - - yes, we are going to complete most of these capacities in FY '26 in addition to Bikaner. So we were hoping that we will commission Bikaner and some smaller project and add 2 gigawatt of capacity from the renewable side. However, as 1 gigawatt Bikaner and all the smaller project of 100 to 200 megawatts add up to that 2 gigawatt capacity.
Okay, my second question cum request is that like earlier investor mentioned, if you can put up a presentation or some file which mentions the project cost, capacity, tariff, and approximate commissioning date, that would be nice.
As you said earlier that, yes, we are going to do the same. Thank you for the valuable suggestion and we'll put up the presentation for the investors.
The next question is from the line of Marsal who is an individual investor.
Yes. My question is that like last time we heard a news that CBI has registered a case of INR191 crores for about 10, 15 years regarding earlier for the 6 senior employees and some contractor employees. Now since SJVN is undertaking a huge amount of project of more than INR50,000 crores, so like what monitoring and internal check and balances mechanism you have put that in the procurement of so much huge amount of capex items, there will not be any such fraud issue?
So you unde rstand that we -- SJVN Limited is a CPSU and a regulated company, we have procedure in place to check all such practices. However, as this is still sub-judice, I don't want to comment upon the specific case. But we can assure you that our systems and processes are in place, and you won't see any such cases in the future.
And second -- very good. And like in the last con call also, I asked a question that like -- and the Chairman gave me a very good answer that because -- sorry, so the question regarding that in O&M a lot of this, for example, amount is being charged by the O&M service provider and majority of it is their profit only because they have the minimum expense of salary? So since you are going to have like 30 gigawatt or 20 gigawatt capacity in the next 2, 3 years. So if we are continue to do the O&M outsourcing to the other company, so it means that will mint the money and we will bleed the money? So the last time the Chairman gave a very positive answer, he said that no, like since the cost structure and the employee salary in SJVN is very high considering CPSU, so you are like in process to form a joint venture with some private company. So where do we stand on this one? Because like very soon, our project will get commissioned. So O&M will be required immediately. So did you already sign some JV for the O&M services with some private player?
No. We have our -- regarding O&M, I must assure you that are the best PSU having the O&M yardstick. Our Jhakri plant is running at 110 PF and the Rampur project is also 109 PF.
No, no, I'm talking about solar capacity, not about the thermal and not the hydro.
You're asking about the solar?
Yes, sir, because in solar also O&M is required?
Yes, yes, yes, but not at that large scale. So we are having some state-wise, some O&M agency or some kind of tender. So that is our strategy that minimum these resources, manpower and other this thing should be deployed for O&M or solar projects. Maybe we are also thinking about having a small company that will look after all the O&M this -- O&M solar projects.
That's what I'm saying because see, last time Chairman said that if you make your own company for O&M, so since it is CPSU, your salary structure cost will be very high. So he said that you are in discussion with some private player so that who is like -- who own a business and then you want to make a joint venture with a private company. So because -- so in that company, the salary can be different than the central government salary scale. So if you do that, our cost will be lower. And since you are setting a gigawatt, gigawatt plant, O&M will be definitely required. But if O&M is outsourced to some third party or third company, like then our cost will be very high and it will become permanent overhead. So please, this is an area for achieving cost efficiency. So like when can you set up this?
So we wanted to share with you that as far as our renewable capacity, especially solar and wind is concerned, whenever we are awarding EPC for initial 3 years to 5 years, we are awarding the O&M also to the contractor. So there, we are not incurring any additional cost. And as you said that, yes, deliberations are in place, and we are actively using the proposals to reduce the cost, especially for our O&M capacity as far as the solar and wind project is concerned. So that is still a work in progress.
Ladies and gentlemen, that was the last question for today. I now hand the conference over to Mr. Rupesh Sankhe from Elara Securities Private Limited for closing comments.
Yes. So we thank SJVN management for giving us an opportunity to host this call. And we also thank all the investors and analysts for joining this call.
Thank you. On behalf of Elara Securities Private Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.