I re-iterate the mistake earlier note that Shri Vamsi Ramamohan Burra, Director (Projects) joined us through VC separately. We will now start with Q&A. Please raise your hand and ask your question is scheduled one by one. Sumit, please go ahead. Sumit, you can unmute your line.
Dec 2024 call
Good morning and thanks for the opportunity. My first question is, if we look at the capitalisation in the nine-month period, there appears to be a steep increase implied for the fourth quarter to meet the target of about ₹180 billion that you had spelt out for FY '25, are we on track? And if I look at the works in hand position mentioned in your presentation. It's similar to what we had heard in the November '24 analyst meet at about ₹1.43 lakh crore. So, what has been the fresh wins that we have seen in the last couple of months? Has that been equal to recapitalisation roughly? Thanks. That's the first question.
Okay. Sumit, what we have shown in the last quarter, actually, this is the works in hand which are to be executed, that is excluding the CWIP. If you see that last quarter, we have done a CapEx of maybe around ₹10,000 crores. So, whatever we have added to that extent, whatever we have done the CapEx, it will come down. That's why it's looking like as if it stands still, but it's not so.
Fair point. And for the fourth quarter, are we on track for capitalisation for the full year?
Yeah. So, we are targeting in the same range about that ₹18,000 crores. That range we are targeting.
Okay. My second question is that what is the impact in Q3 and nine months results of the FY '25-'29 CERC tariff regulations pertaining to O&M and what has been the performance of PGCIL JV EESL in nine- month FY '25? There were losses in 1H, if I remember.
This impact of CERC tariff regulations, the O&M portion is around ₹140 crores in Q3. If you compare the same with the Q3 of FY '24. And regarding EESL, yes, we have not put any equity in the last almost a year, so whatever we have put the equity, it was in the two years back. So we are not putting further equity in that.
Was there any loss contribution from EESL in nine months?
Yes. For the nine months, it is around ₹140 crores, it is included in the consol, our portion, 39% of our stake amounts to ₹140 crores for nine months.
Okay. So, the third quarter will be about ₹40 crores.
Yes. It is cumulatively ₹140 crores.
Yes. Just last quick one to check on the large contract that was won by Khavda by your competitor, what was the difference in bid for Power Grid versus L1? And could you give us -- this had first come to Power Grid, so what was the sequence of events? It's a reasonably large contract?
No, it's not Khavda. Khavda, we won.
Yeah, Khavda was only like, bid was being given by our competitor, and finally, we won. So there were a difference of only 0.25%. Between us, we were the winner in Khavda and between the other party.
I'm referring to the ₹25,000-odd crore project that was won by Adani Transmission.
Yeah that was Fatehpur to Bhadla-III. So, they have won in about ₹3,500 crores and considering the land policy in Rajasthan after this 14th June 2024 and earlier, we won this project in ₹3,700 crores. So, we have revised our bids, and for us the parameters what we decided that we will not go beyond the L1 limit. So that was our stand on the project because it was not coming in our range.
Thank you so much. Wish you all the best.
We request attendees to please stick to two questions per participant. We may be moving on to the person when I unmute, I request the participant asking the question to also unmute on their end before they ask a question. The next question is from Subhadip Mitra [ph] [0:41:18] you may unmute. Since we have no response from their end, we will move to Ketan Jain. Ketan Jain you may unmute your line.
Thank you for the opportunity. Good morning. My first question is on the number of projects won in nine months and 3Q? If you could tell us the cost of the projects won in nine months and 3Q?
Up to December '24, it is ₹63,909 crores. And for Q3, it is ₹19,828 crores.
What is your outlook on the awarding of projects for FY '26? Do you expect like around ₹1 lakh crores worth of projects were awarded this fiscal year. What is your outlook on FY '26? Do you think it will take a pause or do you think it will continue?
Like I have mentioned that as per NEP plan, total for interstate is about ₹6 lakhs. So FY '26 also, it will be similar to FY '25. So we will also have similar figures for FY '26 also. Already, there are about projects worth ₹52,000 crores under bidding.
Understood. My last question is on the same number which you gave for cost. Can you give for tariff, award of projects?
Q3, it is already in the presentation.
Yeah, ₹2,077 crores for nine months.
For nine months tariff is ₹8,027 crores.
Understood. Thank you. Those are my questions.
The next question is from the line of Ketan Jain. You may please unmute your mike.
My questions are done. I just spoke.
The next question is from Akhsay Malhotra. You may unmute your line.
Thanks for the opportunity. I wanted to first of all understand the progress on the intrastate bidding side. And concurrent to that, I wanted to understand that on the intrastate project that we have with Rajasthan, has the work started on that? That's my first question.
Okay. The intrastate projects are being executed by various states like UP and MP and we are also participating wherever opportunity is there. As far as the JV for intrastate with Rajasthan, we have already formed the joint venture company. Our MDs also joined there, and projects are being identified by the Government of Rajasthan. As soon as projects are identified, then they will be taken up for execution.
Okay. Thank you. Also, quickly on the CapEx and capitalisation side. I think you've helped us with the number for FY '25. Could you also, in a similar manner, tell us the expected CapEx and capitalisation for FY '26 and '27?
FY '26 because whatever projects like we have projects about say, ₹147,000 crores in hand and about ₹29,000 crores in progress. So put together, we have almost ₹1,76,000 crores projects which are to be commissioned in next five years, because this includes HVDC Leh to Pang which is to be commissioned in the next five years. And similarly, our Khavda to Nagpur that is also to be commissioned in next 4.5 years. And then we have offshore project also, that is also to be commissioned. So, if we subtract these costs, so AC section will be about ₹1,08,000 crores projects are to be commissioned in the next three years. So, every year, that means next year, we will have target about ₹25,000 crore projects, which will be required to be commissioned. And next year, may be about ₹35,000 crores and maybe next year another ₹35,000 crores. So, it will be in that range.
Okay. So, this is the capitalisation number, right?
Yes, capitalisation.
And similar to that on the CapEx side?
CapEx, like this year, we are telling it is about ₹23,000 crores up to March. And for FY '26, it will be in the range of about ₹28,000 crores to ₹30,000 crores. And for next FY '27, it will be again ₹35,000 crores.
Okay. That would be very helpful. Thank you.
The next question is from the line of Bharanidhar Vijayakumar. You may unmute your mike.
So, I want to ask the regulated equity in the RTM projects as at end of December '24 that we have been investing?
Regulated equity, see, we have given you that our net worth is like ₹91,000 crores and then we have put ₹4,390 crores, plus another ₹400 crores in the TBCB companies. If you deduct that and then you deduct another around ₹2,000 crores to ₹3,000 crores, which we have put in another JVs and in telecoms, roughly, you take out around ₹10,000 crores. So maybe in the range of ₹80,000 crores to ₹83,000 crores will be the regulated equity. It's very simple mathematics. Just you see the net worth and then remove the JV's investment and TBCB, SPV investment and then you get the regulated equity. Plus, we don't have any other business in the standalone.
Understood. So related question to that is how much of equity would be required to be invested in the upcoming projects over the next three years?
Normally, we put 80-20 for the TBCB projects and all the regulated projects, we stick to 30% at least to the equity, because we get the 15% return. If we reduce less than 30%, it's loss for us. So, we put maximum threshold of 30% in regulated projects. And TBCB, it's free for us to put any equity, but so far, we are almost maintaining 20%.
So, if you consider say ₹25,000 crores CapEx next year, so maybe between ₹5,000 crores to ₹6,000 crores will be required including TBCB and RTM projects.
Got it. My second question is on the execution challenges in developing transmission projects. Some of the equipment manufacturers and other developers are highlighting challenges in land acquisition and equipment supply, say be it high voltage transformers or some conductors. So, what is your view on it? And would we be able to execute and commission our pipeline of projects within time? Or in your assessment, what could be a conservative estimate of risks? And how much can project get delayed on an average?
Yeah. The challenge of the procurement of these high-value items, especially transformer and GIS it is a real challenge. So, we are mitigating this challenge by procuring under bulk procurement, transformers we are procuring irrespective of the projects in hand. So, we are ensuring that we have adequate number of transformers and reactors with us for meeting the requirement of future projects. And as far as GIS is concerned, so there are challenges, especially for GIB part. So, we are discussing with GIS suppliers so that they can start manufacturing in India. And now they are also ramping up their manufacturing capacity, GIS as well as transformers and reactors.
Sure. Okay. That answers. But if you could give some estimate of would project, be delayed? Meaning if project timeline is say 1.5 years to two years, in the best case scenario, would you expect for our projects on an average, the project commissioning would be say 2.5 years, three years? In reality, would that be the case?
Yeah. Normally, whatever two years' time period, we are trying to achieve, especially for any substation wherever transformers or reactors are to be commissioned. So, we are ensuring that all the equipments are commissioned on time, but especially for transmission line where RoW issues are being encountered. In some cases, there are challenges. So, some delays are happening because of RoW issues. But still, we are taking up with the Ministry of Power and the state administration to minimise the delays but let me accept that there are challenges in completion of these transmission projects within two years.
Thank you so much. All the best.
The next question is from the line of Tanveer [indiscernible] [0:54:25]. You may now unmute your line.
Yeah. So actually, I am a shareholder in Power Grid and the Power Grid InvIT as well. I had a simple question. This Power Grid InvIT was set up with the vision of monetisation of Power Grid assets, but that plan seems to have been dropped. So there are a lot of shareholders, including our parents and senior citizens who have put their hard earned money in Power Grid InvIT. And if you see it raised funds at IPO around ₹100. Today, the share price is nearing ₹80, primarily because it is unable to get any assets and raise its DPO. Now I understand that Power Grid is the sponsor there. So I just wanted to understand, so much faith we are putting in the government and Power Grid, doesn't Power Grid have any plans to monetise assets via this trust?
Yeah. When we came out with this PG InvIT, as per that guideline existing at that time, we were planning to disinvest some assets in PG InvIT. But after new NMP guidelines, now we are not able to disinvest our assets in this PG InvIT, so we don't have plan in near future to disinvest our Power Grid assets because of NMP guidelines.
Then what will be the entire purpose of that trust? I mean the sponsor of parent is itself is going to just abandon this particular trust and how is it supposed to function?
No, see, the initial InvIT was found to monetise the commissioned assets and subsequently, when you see in the August '21, the National Monetisation Pipeline guideline says that the asset of the shareholding is not to be transferred permanently, it is only permitted to transfer the revenue rights. So, when we examine the revenue, rights are to be transferred to the InvIT or any other entity, it attracts a GST of 18%, which is, again, not lucrative to the shareholders of Power Grid, because ultimately in the transmission charges, if you get after discounting 18% GST, it's not value decretive. So that is why this process could not be carried out. So that is the reason that Power Grid has started doing the securitisation of the SPVs. So, it is because of the guidelines.
I think we should have to take out this in the Investor Meet of the other listed entity because this is a separate listed entity. I think this will have a conflict of interest of answering the questions of the PG InvIT here.
Yes, with that management...
I request you to please join the queue again if you have further questions.
Okay. Thank you.
The next question is from the line of Bhalchandra Vasant Shinde. You may please unmute your mike and go.
Hello, good morning. Can you provide HVDC pipeline over the next two years with value worth where we see traction, which where we can add up in our CapEx?
We have already two projects in our hand, one is Khavda to Nagpur, which is almost worth ₹35,000 crores, although NCT cost wise ₹24,000 crores, but as per the market conditions that cost is going to be about ₹35,000 worth crores. Second one is Pang to Leh, which is, again, more than ₹20,000 crore project, which will be executed in the next five years. Already it is under bidding. And other than these two projects, one project had been won by Adani, which is Bhadla to Fatehpur. Then two more projects are coming under bidding. One is already under bidding from KPS3 Khavda to South Olpad, with NCT cost of about ₹12,000 crores. Then there will be two or three more HVDC project, one from Rajasthan to Maharashtra and then one in Andhra Pradesh. In near future, these projects are visible, which will be under bidding shortly.
Got it. And the figures which we have mentioned in our NEP plan framework, when we add up based on your guidance, overall CapEx for next two years translates to around something around ₹3 lakh crore. Is it fair to assume that ₹3 lakh crore kind of a CapEx will happen as per the plans in NEP?
For Power Grid or for total?
For total.
Got it. Thank you. I'll come back in the queue.
The next question is from the line Aman Jain. You may now unmute your line.
Hi, thank you for taking my question. So, my first question is regarding the Bhadla-Fatehpur HVDC line where bid was annulled. So, A, what was the reason for cancellation? And B, in the rebid another player won the project for like ₹25,000 crores, while we had secured it earlier for ₹12,700 crores. So, like was there any change in the scope of work? And if not, what led to a significant lower bid compared to the final awarded amount, which was almost twice? So, if you could give some colour?
You're talking about Fatehpur-Bhadla?
Yes.
Like NCT cost in case of Khavda-Nagpur was ₹24,000 crores, whereas actual cost when we go to market, it is depending on various factors. Now I'm saying that total executed cost will be somewhere ₹35,000 crores. So similarly, in the case of Fatehpur-Bhadla also, although NCT cost was ₹12,000 crores, but the executed cost may be about ₹24,000 crores, ₹25,000 crores. But now we are not executing that project. So exact figures can be given by the transmission developer, which is Adani. So, we cannot comment on that.
Okay. Thank you. Got it. My second question is regarding revenue from operations declined 3% Y-o-Y. So, any reason for that?
See, the structure of the regulated tariff income means that it will decrease every year because of the interest on loan, which will be reducing based on the depreciation recovery. So, if I recover around ₹12,000 crores, ₹13,000 crores of a depreciation, to that extent, if you say a thumb rule like 7.5%, 8% at the interest, so naturally around ₹700 crores to ₹800 crores, ₹900 crores for transmission income is bound to come down every year. But the fact remains that the PAT will remain same because that is based on the return on equity. So, the transmission income of the regulated business is bound to come down. This is what the structure, the one-time expenditure will increase, whereas the interest on loan will come down, but the PAT will remain same. So that is why the reason that it will come down. But when we commission new assets, it is again added. That is why it's not reducing to that extent. So, when I say that when the revenue is supposed to come down by like ₹800 crores, ₹900 crores in a year and if you compare for the nine months, maybe around ₹600 crores, ₹650 crores, it is bound to come down, but it is not coming down because we are adding more assets.
Got it. Thank you.
The next question is from the line of Satya. You may unmute your line. Since we have no response from Satya, we will move on to Mayank Bora. You may unmute your mike.
Thank you for the opportunity. I just wanted to know what was the borrowing cost of this $200 million from Sumitomo?
It is based on the TONA is the reference rate and the borrowing interest rate is around 1%, including the spread. We'll have a foreign exchange rate variation. Whatever is depends on the movement of the Japanese currency.
Okay. So, we have any plans to reduce our domestic debt and replace it with the foreign debt?
No, not required to be replaced. But since we have a huge pipeline of CapEx and we have to raise more and more debts, we can explore further debt through other markets instead of domestic. We should have a mix, so we can mix something as to the other currencies instead of sticking to only to INR because last four, five years when this SOFR was trading at close to 5 or 4.5, so we refrained from going to the other markets for the last four, five years. Now since the TONA is almost at a very competitive rate, we are exploring the other markets. So maybe since this comes up with a greenshoe of another 150 million, so this is 200 million plus another $150 million will be close to ₹3,000 crores, if you convert it into Indian rupees. So further, we will explore the same similar type of markets.
Okay. Thank you for the opportunity.
Thanks. It's kind of a follow-up to the previous question. So, I just wanted to understand that by taking these green loans, is there any material change in your cost of debt that you're expecting going forward?
Yeah. Naturally, the other markets, whoever the lenders, encourage the green loan, and we expect that there should be a benefit in the rate of at least for a few bps.
Got it. And just secondly, could you highlight your CapEx and capitalisation numbers for the standalone company?
As our chairman has already told that we have a pipeline of almost ₹1 lakh crore of our projects, excluding the HVDC and offshore projects, which have a time line of another three years for commissioning. So maybe in the range of ₹25,000 crores to ₹30,000 crores, the commissioning will happen for the next three to four years.
Understood. Just wanted to understand because the RTM projects would be in the standalone company if I'm not wrong. So, for that, I just wanted to understand the broad kind of CapEx.
RTM, we have offshore and Pang-Kaithal, which is around ₹22,700 crores plus another ₹13,600 crores. If you add this, this will be around ₹36,000 crores. And then few bays extension, the others will be there. Around ₹40,000 crores to ₹45,000 crores you can assume we'll be adding up in the regulatory business also.
Sure. Thanks.
Due to the paucity of time, we would like each participant to stick to one question please. We will now move on to Anuj Upadhyay. You may unmute your mic.
Okay. So, majority of the questions have been answered. Just to get one sense, you mentioned that the current year capitalisation target is ₹18,000 crores. We are already halfway mark of the Q4 quarter. You said until Jan, the capitalisation number had been closer to ₹8,000 crores. So, could you elaborate further on which are the big-ticket size project and at which stage that gives us the confidence that in the next 45 or 50 days, you'll be adding ₹10,000 crores of project?
Yeah. I will give the names of the projects. One is Narela project. Narela station is almost ready. Station is ready to be commissioned. But because the connecting transmission line because of RoW issues are yet to be completed. So, we are expecting that at least one or two lines will be completed by March. So, with this transmission line and substation at least ₹1,500 crore assets will be added here. Then Khavda-II and Khavda-III, KPS2 and KPS3, these are two GIS stations. Each will be in the range of about ₹1,000 crores. We have GIS, transformer, then transmission line between Khavda-II to Khavda-III. Similarly, Khavda-III is also GIS, where transformers, reactors and the GIS station is there. So, each will be ₹1,000 crores and ₹1,000 crores, so put together ₹3,500 crores. Then we have Ahmedabad, Ahmedabad- Banaskantha transmission line, then Navsari station; Navsari, again, GIS station. Then Navsari to Magarwada, this line is almost getting ready by February, and we are hopeful that this project will also be commissioned by February, this will again be in the range of about ₹1,500 crores. And one more project in Kurnool, Andhra Pradesh. Kurnool station is getting ready in another 20 days and transmission line from Kurnool to Kurnool from existing we have Kurnool-II station. And from there to new Kurnool-III station transmission line is almost in advanced stage of completion. So that will also be commissioned. So that, again it is going to be in the range of about ₹1,500 crores. And similarly, we have projects in Northeastern region like Namsai to Kathalguri, GIS at Kathalguri and Namsai both and transmission line and some projects in NER and Eastern region reconductoring projects and in Odisha. So, if these are all projects are in advanced stage of completion. One more project in Rajasthan is Bhadla to Sikar-II, which we are trying to complete, but it is very difficult, but we are trying to complete this project also. So put together, we are expecting that around ₹10,000 crore assets are likely to be completed by March because all are in advanced stage of completion.
This is super helpful. Thank you. And if I just ask one more question on the smart meter update on the Gujarat contract and any new states where we are in advanced stage of getting an opportunity?
For smart meters, we have this order of about 67 lakhs meters to be installed in Uttar Gujarat and Madhya Gujarat. And what we are planning that, once we have experienced with these meters in Gujarat, then only we will consider next state. But so far, we are not considering any other state other than, we are focusing on completion of this project.
The next question is from the line of Apoorva Bahadur. If you may unmute your mic and go ahead.
Thank you for the opportunity. We noted there was a reduction in the interim dividend per share, right, for the nine months so far. Can you throw some light on that, why it was a requirement for this?
Like, as you understand that last year, our CapEx was ₹12,500 crores. This year, it is going to be ₹23,000 crores. And in FY '26, it will be still more. So, we require more and more equity to be infused for our CapEx requirements. So that is the reason we are slowly, slowly, we may go further down. Today, we have ₹4.5 was the first dividend, and this is a second interim dividend, ₹3.25, so put together ₹7.75. So, we are hoping that we will be somewhere in the range of about ₹9 in this financial year. So, it is because of the CapEx requirement.
Understood. And when I see your CapEx guidance for the next two to three years, it seems like we plan to do almost ₹60,000 crores, ₹65,000 crores of CapEx for FY '26-'27 maybe around a similar number for '28 as well. But the work in hand is still higher, right? So, in case even if it is spread out over four to five years, do you think that there is a possibility of further upgrading the CapEx number, especially for '27?
'27, there are possibilities because there are a number of projects which are under pipeline. So, considering those projects, maybe FY '27, it may go more than ₹35,000 crores also.
Okay. And lastly, on the HVDC project orderings, when do we expect to see those for both the projects in which year?
HVDC project Khavda-Nagpur is already ordered, it is ordered on Hitachi. And work has already started, our design engineering work is going on. And at site also, we have already done Bhoomi Puja. So now execution will start very shortly. As far as this second project of Pang- Kaithal because it is a very challenging project, still there are queries being raised by prospective bidders like Hitachi and Siemens. And we are expecting that queries will be clarified to these bidders and then we will get that bid. And maybe in the first quarter of FY '26, it is likely to be awarded.
Sure. Thank you so much. All the best.
Hello everyone. Thank you for this opportunity. I just have one question. Could you please elaborate a little more on the regulations around the National Monetisation Pipeline and clarify more on the asset transfer and revenue transfers?
You see, National Monetisation Pipeline guidelines was published in the month of August 2021, and it envisaged that the assets of the central CPSEs are not to be transferred permanently and only the revenue rights are to be given. And that is the reason that we have not further added the assets because once we have to add the assets means, we will have to transfer the shares, which is not permitted in the National Monetisation Pipeline guidelines. So, of our monetisation, we have adopted the route of securitisation of the cash flows and through which we raised the bonds and then we opened TRA account where we used to put the money for servicing the debts.
Okay. And could you clarify about the GST payment in case of a revenue transfer, please?
Yeah. In case of, if you transfer the revenue rights, so that is not treated as a transmission charges. These are all considered as a lease charge for which GST is to be paid. So, the reason that if I transfer the revenue rights, so whatever money I get as the NPV, I will have to pay 18% as the GST. So that is not a lucrative transfer.
Okay, thank you so much.
The next question is from the line of Vikram Datwani. You can please unmute and ask your question.
Thank you for the opportunity. Just one bookkeeping question for me. Could you please share the nine-month impact of the CERC tariff on O&M? You alluded to the Q3 figure at ₹140 crores, but could we get the nine-month figure as well?
You can multiply by 3, it will be in the range of around ₹450 crores.
Okay, thank you.
I just wanted to check. You indicated about ₹52,000 crores of projects under bidding. So just trying to understand, what is the potential pipeline of projects, which can be added to this, A? And B, you also spoke about potential HVDC projects in Rajasthan and AP. What is the potential size of these projects? Also, there is a news flow of this Andaman HVDC project on a RTM basis, right? So is it safe to assume that Power Grid will be executing this project? And what could be the tentative timelines over here? If you can provide some colour on that, please?
Okay. Yeah, this ₹52,000 crores when you say that we have a traditional strike rate of 50%, you can say that when this bidding happens may be we'll be able to add another maybe ₹25,000 crores to ₹27,000 crores. So, when I say today, ₹1,43,000 crores, you add another ₹27,000 crores, so this will become around ₹1,70,000 crore. And your follow-up question is on the RTM project of Andaman. It is not in a mature stage. So as of now, there is no concrete development or we got any intimation of getting that through RTM. Once it comes, we will naturally inform.
Sure. and lastly, I mean, what explains the fall in consolidated profit in this quarter despite the rising capitalisation. Is it largely driven by the O&M expenses? Or is there something else or if you can help us understand it better, please?
You see, only if you see in Q3 to Q3, there will be a reduction between consol and standalone, that is because the dividends which we have taken from the SPVs is more than the Q3 profits of the consolidation of all SPVs put together. That is the reason. And as far as consol of nine months is concerned, you see there is an increase from standalone to consol.
I was looking at consol to consol only, Q3 to Q3, there's a reduction in profit.
That is because actually, we have a loss of some of the JVs like we have one JV EESL, which was our share of loss is ₹140 crores. So that has slightly pulled down in the consol because that's not figuring in the standalone.
And in addition to that, if you see, there are one-off items in the previous years, like we have one-time CERC order impact and interest and differential the orders between the doco date and the order dates, these are all normally to some extent, it will contribute more to the bottom line, so which is lesser in the current year. That is also the reason that your PAT has come down compared to last year.
Sure. Lastly, if I may, how should we look at the dividend flow from here in view of the rising CapEx? To understand what the outlook is on this? If you can provide some colour?
Dividend, we have a policy that we will give the dividend, we will not keep the idle cash as well as we will, part of our CapEx also. So we will strike a balance between these two. And going forward, when we commission more and more projects, naturally, the revenue as well as PAT also will increase. So that also will add to maintain the dividend to some extent. It's not going to fall very steeply to like ₹2 or ₹3 something like that. It's not even permitted as per the DIPAM guidance also.
Sure, got it. Thank you very much and all the best.
We have our last question of the day from Mohit Pandey. You may unmute your mic and go ahead.
Just one question. So, for the Leh-Kaithal project, has the technology been decided whether it will be LCC or VSC?
No. From the start itself that we are executing this project at VSC only, not LCC.
Understood, thank you. Thank you so much.
With that, we'll conclude this meeting. I would like to thank the senior management of the Power Grid for taking the time out for this analyst meet and addressing all the queries. I also would like to thank all the investors and analysts for attending the meeting. Thanks, everyone. So, would you like to conclude if you need to make any concluding comments?
So, thank you, everyone for your time and sparing your time and having interest in Power Grid. So, I can assure all the investors and our shareholders that Power Grid outlook is very bright. And we have many projects in hand, and our project capitalisation and CapEx is going to increase. So that will lead to increase in revenue and profit. So, our Power Grid future is bright. So, rest assured, you are in safe hands.
Thank you. Thank you, everyone. Thank you. With this we will conclude. Thank you.